Monday, September 28, 2009

First Floor Framing


Framing has begun and most of the first floor is complete. Engineered joists and beams have been used to carry the loads across the open floor plan.

Monday, September 21, 2009

Utility Installation and Block Completion



All CMU block has been installed and waterproofed. Water and sewer connections have been completed. The first floor lumber has arrived and framing will begin soon.

Friday, September 18, 2009

CMU Insulation



The concrete block has been filled with Tripolymer two part foam insulation. It has a shaving cream consistency when wet and a powder/plaster texture when dry. This insulation brings the total R value of the block wall to R-17.7.

Wednesday, September 16, 2009

Slab Poured and Finished



The concrete slab has been poured and troweled smooth. Saw cuts have been made to add visual interest and reduce random cracking potential.

Tuesday, September 15, 2009

Slab Preparation


The foundation has been prepared for the concrete to be poured. Two inch insulation board has been installed over the entire area where the concrete floor will be. A vapor barrier and wire mesh has been added to complete the preparation.

Wednesday, September 9, 2009

Block and Plumbing


The first three courses of block have been layed and waterproofed. Rigid insulation board has been installed vertically on the inside of the block. The plumbing that will be in the concrete slab has been roughed in.

Tuesday, September 1, 2009

Foundation Footers



Footers have been dug and poured. Surveyor has completed the block point survey and CMU installation begins soon.